18 September, 2020
At Minsk TPP-3, construction and installation work is underway on a planned basis for construction of a new steam boiler E-500-13.8-560 GM manufactured by Machine-Building Factory of Podolsk.
15 September, 2020
JSC Machine-Building Factory of Podolsk promptly shipped the last batch of exhaust system equipment with a flue gas discharge device for Amur TPP.
13 July, 2020
Machine-Building Factory of Podolsk received the support of the Russian Export Center for implementation of a project for reconstruction of TPP of JSC Sokolovsko-Sarbayskoe Mining and Processing Production Association in the Republic of Kazakhstan.
23 July, 2020
The company "System Software" provided help to JSC Machine-Building Factory of Podolsk in transferring its employees to "remote work" mode.
22 June, 2020
Machine-Building Factory of Podolsk JSC signed a contract for the supply of two steam turbines complete with ID fan gear boxes for primary methane conversion furnace of TOAZ PJSC.